§ 2-691. Modification of contracts.  


Latest version.
  • The procurement director is authorized to adopt regulations permitting or requiring the insertion in contracts of appropriate clauses to enable the county to effect desired changes and modifications to such contracts; provided however, that any such change or modification, except for road and/or bridge construction, which would result in additional expenditures by the county in the sum of $25,000.00 or any such larger sum only shall be effected after appropriate authorization and approval by resolution of the commission.

    Change orders less than $100,000.00 for road and/or bridge construction must be authorized by the mayor. Change orders for an amount of $100,000.00 or more must be authorized by the mayor and approved by resolution of the commission.

(Ord. No. O-08-5-101, § 2(Exh. A), 6-23-08; Ord. No. O-10-11-101, §§ 1, 2, 12-17-10; Ord. No. O-16-3-101 , § 1, 4-25-16; Ord. No. O-18-7-101, § 1(Exh. A), 8-27-18 )